Business

 
  • Red Creek Power Substation One of a Kind

    09/23/2026 - 15:25 , by live
    SAN ANGELO, TX — Data center developer Cipher Digital told the Tom Green County Commissioners Court Tuesday it picked the county for one reason: the Red Creek substation. The AEP Texas Red Creek 345-kV Station off City Farm Road is the crown jewel attracting two large-load data center projects to the San Angelo area. Two companies, Emergent and Cipher Digital, on adjacent plots of land, are vying for an interconnect with the station for juice to power a 1.2 GW and a 1 GW facility, respectively.